Wednesday, 23 December 2009
091223 Site visit
Assembly Hall footings covered in snow
Gas awaiting connection- no date confirmed at present
Snow and ice covers classroom slab/ progress on blockwork
Blockwork to classroom block
Obsolete RWP connection to G/L 4/D
Render being removed from Otway may take face from facing brick
Render issues also present to Otway G/L E/11
Closer inspection of Ibstock Bevern dark reveals chips to headers in batch
Ibstock Bevern dark- possible chipping when repacked
Ibstock Bevern- chipping will not be acceptable for header bond
Thursday, 17 December 2009
091217 Site visit
Assembly Hall prep below slab
Otway scaffold nears completion
Gas diversion awaiting connection
Gas diversion pending connection
Gable end elevation brickwork to Otway House underway
Gable end return- rendered area may require additional facework when removed
Mortar Silos now installed- Terracotta D Class 1 (below dpc) and mortar for blockwork
Blockwork rebuilt with mortar from silo
Concrete columns to classroom block- formwork removed
Otway gable end elevation 1/2 brick thicker
Otway fireplaces blocked up to first floor
GSHP manifold installation
Wednesday, 16 December 2009
091210 Site visit
Thursday, 3 December 2009
091203 Site Visit
Black glazed bricks from HG Matthews- not as sample
HG Matthews Grey glazed bricks- not as original 'silver sample'
Pitting to grey glaze not as original samples
Manhole 16- G/L Q
Footings- Assembly Hall
Concrete slab to classroom complete- RIW Sheetseal laid to perimeter
Blockwork commenced to classroom block
Sheetseal to edge of ramp
Blockwork Classroom block
Water ingress still apparent in Otway House- ground floor and first floor