Wednesday, 26 May 2010

100525 Site Visit

 

Test panels of patterned relief and coloured brickwork


Existing Otway roof structure reinforced by steelwork


Otway  first floor private study with internal window to stair and exposed roof structure above

Arches exposed by demolition work in poor condition

Monday, 24 May 2010

100520 Site Visit


Site overview from Ingrave Road- Classroom block


Site overview from Ingrave Road- Otway/ Assembly Hall


Interface between steel/ block- awaiting intumescent


Ditto- int. mastic required to joint


Plywood/ tek screws discussed for brickwork support to steel low level opening


Gutters/ ply deck in progress


Gutters- DGT to provide support/ calcs for rainwater


Corner gutter- support under to be clarified by DGT


Strap detail to high level roof perimeter


Overview of gables assembly hall


Flaunching- review method to deal with cracking


Flaunching to be redone where pots replaced


Gable end Otway timbers


Ditto


Arch repair Otway


Ditto


Brick repair- mortar colour to be reviewed/ discussed further with conservation officer 25.05.10


mortar to rebuilt chimney


Openings formed 1st floor Otway


Steel downstand beams to Teapoint GFL- CVA to review removal


Beams above- 3 No. timber joists requiring replacement if steels removed


Blockwork Classroom 2FL- proceeding


Reveal detail incorrect- to be modified to allow for differential movement of internal and external skins


Ditto


Edge beam GL D/1


GL D/3- edge detail discrepancy still to be confirmed


Possible knotweed plant adjacent substation

Monday, 17 May 2010

100513 Site Visit


Assembly hall- gutter being installed to high level roof by DGT


Assembly Hall- Metsec/ insulation nearing completion to walls


Gutter being installed GL Q/16


Gutter installed GL P/18


Minstrel's Gallery- control room awaiting penetrations within floor/ trimming steels


Hutton mark up discrepancies within Assembly Hall high level reference panel


Gutter/ outlet position GL Q/16. Outlet positions not generally as drawn. HUT to review all positions/ downpipe connections


Outlet/ gutter GL Q/18


Outlet GL Q/14- clash between plate and downpipe


Minstrel's Gallery- progress to Metsec/ insulation/ roof deck


Detail/ COI required for local areas over door to courtyard- Assembly Hall


Roof gutters in progress


Window openings formed in Metsec


Blockwork GFL complete Assembly hall plinth area


Gaps maintained for Intumescent treatment


Classroom 2nd floor slab- more localised cracking GL A-B/1-2


Beam cast GL 2-3/C-D


Blockwork underway 2nd floor classroom block


Precast stair 1st to 2nd floor installed


Lintel installed Otway GL G 1st Floor


Setting out amended to partial height wall GL H


Steel beam taking Chimney C


Steel/ valley beam exposed


Openings formed- partial height walls around Otway stair


Tie exposed to existing wall GL I/11 1st floor- Hutton to propose casting in to padstone


Classroom block- pointing discoloured GL 1 chimney