Monday, 28 June 2010

100624 Site Visit


Infill recessed brick panel GL D/3


Structural remedial works GL C/ 6-7


Window reveal detail to be reviewed CL.EW.01.08


Classroom Ring beam w/ voids form in locations for rainwater outlets


Voids formed under ring beam for insulation to deep reveals


Ring beam form work


Ring beam curing


Classoom block GL D/ 2fl


Classroom block overview adjacent link


Base to chimneys 3 & 4- phenyl board to be modified before pour


Classroom brick/ block underway GL 4, 2nd fl


Classroom block overview from Assembly roof


Assembly- Rainwater outlet/ fall in insulation to be updated/ instructed GL K/20


Assembly- wind post plates being installed to gables


Detail of plate


Bauder to rooflight upstands


Oulet formed in Bauder membrane


Setting out of hatch/ internal lining to be reviewed/ repositioned


Overview of Assembly high level roof with bauder membrane in progress

Monday, 21 June 2010

100618 Site Visit


2nd floor classroom blockwork gable underway


Assembly main roof bauder membrane underway


Gap between rooflight and access hatch


Overview of main roof assembly hall


detail of upstand


membrane scuffed- to be addressed


bauder membrane to assembly rooflight upstands


roof membrane underway


Wind posts ground floor classroom block- clerestory openings to follow


Classroom block 2fl corridor in blockwork


double gable elements progressing to classrooms 2fl classroom block


shuttering to underside chimney- to be rectified as not continuous phenyl board


Remedial works to 1fl slab- classroom block


Otway gable end- brickwork details


Otway gables meeting- detail underway- awaiting flashing


Otway gables meeting- detail underway- awaiting fascia/ final brick


Otway ring beam preparation underway high level 1fl perimeter


Cut-out for Otway rooflights

Friday, 11 June 2010

100610 Site Visit


Overview of classroom block


2nd floor blockwork to classroom with re-bar for ringbeam


Blockwork to 2nd floor classroom block


Blockwork 2nd floor


Blockwork gfl classroom- windposts/ clerestory lights


Roof panels high level assembly hall


Plenum assembly hall ground floor


Assembly ground floor- roof nearing completion


1st fix mechanical underway assembly


1st fix mechanical underway assembly


Valley beam replacement Otway


Floor replacement Otway


Brickwork to assembly hall plinth commences low level


AHU installed assembly plant room