Monday, 28 June 2010
100624 Site Visit
Infill recessed brick panel GL D/3
Structural remedial works GL C/ 6-7
Window reveal detail to be reviewed CL.EW.01.08
Classroom Ring beam w/ voids form in locations for rainwater outlets
Voids formed under ring beam for insulation to deep reveals
Ring beam form work
Ring beam curing
Classoom block GL D/ 2fl
Classroom block overview adjacent link
Base to chimneys 3 & 4- phenyl board to be modified before pour
Classroom brick/ block underway GL 4, 2nd fl
Classroom block overview from Assembly roof
Assembly- Rainwater outlet/ fall in insulation to be updated/ instructed GL K/20
Assembly- wind post plates being installed to gables
Detail of plate
Bauder to rooflight upstands
Oulet formed in Bauder membrane
Setting out of hatch/ internal lining to be reviewed/ repositioned
Overview of Assembly high level roof with bauder membrane in progress
Monday, 21 June 2010
100618 Site Visit
2nd floor classroom blockwork gable underway
Assembly main roof bauder membrane underway
Gap between rooflight and access hatch
Overview of main roof assembly hall
detail of upstand
membrane scuffed- to be addressed
bauder membrane to assembly rooflight upstands
roof membrane underway
Wind posts ground floor classroom block- clerestory openings to follow
Classroom block 2fl corridor in blockwork
double gable elements progressing to classrooms 2fl classroom block
shuttering to underside chimney- to be rectified as not continuous phenyl board
Remedial works to 1fl slab- classroom block
Otway gable end- brickwork details
Otway gables meeting- detail underway- awaiting flashing
Otway gables meeting- detail underway- awaiting fascia/ final brick
Otway ring beam preparation underway high level 1fl perimeter
Cut-out for Otway rooflights
Friday, 11 June 2010
100610 Site Visit
Overview of classroom block
2nd floor blockwork to classroom with re-bar for ringbeam
Blockwork to 2nd floor classroom block
Blockwork 2nd floor
Blockwork gfl classroom- windposts/ clerestory lights
Roof panels high level assembly hall
Plenum assembly hall ground floor
Assembly ground floor- roof nearing completion
1st fix mechanical underway assembly
1st fix mechanical underway assembly
Valley beam replacement Otway
Floor replacement Otway
Brickwork to assembly hall plinth commences low level
AHU installed assembly plant room