100702 Site visit


Fan coil unit 1st fix classroom block IT rooms


Toe to 1st floor slab/ chimney.


Edge cast insitu- finish very poor.


Otway rooflights setting out/ carpentry


Valley adjacent rooflights- CVA to confirm setting out


Classroom block ring beam detail underway


Brickwork adjacent tread main stair classroom block


Ditto, below stair


Block setting out required for all TEK vents


1st fix mechanical classroom block GFL commences


Remedial works to Omnia continues


Omnia remedial works complete adjacent link


Brickwork support to Assembly- plinth high level


Screed to plant room laid to fall- assembly


Brickwork commenced GL Q assembly


Brickwork support assembly for installation


Non-relief pattern. Best face to always be used for headers


Some misalignment in isolated areas GL Q assembly


Bed joint reinforcement required to corners- 1200mm every three No. courses