Tuesday, 6 July 2010
100702 Site visit
Fan coil unit 1st fix classroom block IT rooms
Toe to 1st floor slab/ chimney.
Edge cast insitu- finish very poor.
Otway rooflights setting out/ carpentry
Valley adjacent rooflights- CVA to confirm setting out
Classroom block ring beam detail underway
Brickwork adjacent tread main stair classroom block
Ditto, below stair
Block setting out required for all TEK vents
1st fix mechanical classroom block GFL commences
Remedial works to Omnia continues
Omnia remedial works complete adjacent link
Brickwork support to Assembly- plinth high level
Screed to plant room laid to fall- assembly
Brickwork commenced GL Q assembly
Brickwork support assembly for installation
Non-relief pattern. Best face to always be used for headers
Some misalignment in isolated areas GL Q assembly
Bed joint reinforcement required to corners- 1200mm every three No. courses