| Assembly Hall gutters, to replace previous incorrect installation arrive on site |
| First AH gutter is moved into place by DGT. |
| Water still pouring onto Assembly Hall floor. |
| Soffit of suspended Assembly Hall ceiling being installed with unistrut drops below for ductwork support and acoustic panel support. |
| Fixing of AH ceiling up to high level structure |
| Extent of AH ceiling at end of site visit with opening for rooflight |
| Otway House entrance hall with existing tiling below protective flooring, fixing of radiator R9 here to be clarified. |
| OH, fixing of radiator R12 on existing tiled floor |
| Floor joists in place on OH ground floor abutting windows to be boarded from inside |
| Insulation to Otway rafters not completed, insulation on site |
| Breather membrane and battens laid onto majority of Otway roof |
| Stepped central valley gutter, now in 5 bays, being formed |
| Rooflight openings adjacency to valley board. Note that bottom rooflight will be 150mm above shown opening. |
| Leadwork being prepared |
| Lead valley with brather membrane and eaves felt dressed over & into valley. | Lightning conductor's contact with lead valley has been flagged up in site visit report. |
| Correct line of Otway eaves following amendments discussed with roofer at previous site visit |
| Reduced fascia board depth to achieve required last slate level with vent |
| Salvaged slates ready to be laid onto visible face of Otway roof |
| Classroom omnia mist coat, ongoing |
| Classroom omnia mist coat, ongoing |
| Classroom omnia mist coat, ongoing |
| Classroom omnia mist coat, ongoing |
| Back-to-back trunking chasing. To be reviewed with EHRW & MFLLP |
| Raked wall along Classroom gridline 1. Capping to be added. Area to check whether distance from capping to windpost is adequate. |
| Raked wall along Classroom gridline D. Area to check whether distance from capping to windpost is adequate. |
| Otway - Assembly link at first floor. Steel installation internally and externally to be checked with respect to protecting the adjacent voussoirs arch (out of picture) |
| 300x200 flush access panel at high level required in Otway at riser 2. |
| small 150x150 flush access panel at low level . NB. If control levers (above) can be moved to this level then one hatch would be preferable and more convenient for maintenance. |