Tuesday, 19 April 2011

110414 Site Visit


Assembly Hall overview- sedum blanket installed


Hard landscape/ soft border underway to classroom block


Trees felled to Ingrave Road


Otway/ Assembly hard landscape underway adjacent green room/ lobby


Acoustic panels installed top floor classrooms


Assembly stair panelling underway


Otway timber floor laid


Water fountains installed- tiling required- CVA to confirm


CL stair acoustic panels installed 2FL ceilings


Classroom 11- awaiting vertical acoustic panelling


Stair battening- awaiting acoustic panelling- classroom stairs


CL link- Praesposters court underway


TEK internal grille- RAL 9010 as wall


Security box dummy only- to be removed (not on approved drawings)


Handrail/ ramp underway to Assembly hall adjacent Ingrave Road


Ditto


Praeposters Court underway


metal profile reveals/ head flashing underway to GL A CL block


Deep reveal head flashing w/ drip- CL block


Shallow reveal head flashing w/ drip- CL block


Assembly Hall overview


Assembly hall stair cladding underway


Ditto


Curtain pocket formed AS hall


Closing piece required between fineline glazing and trench heating- now instructed


Bleachers installed


Otway tiles- to be replaced where damaged


Bleacher overview from Minstrel's gallery