Assembly Hall overview- sedum blanket installed
Hard landscape/ soft border underway to classroom block
Trees felled to Ingrave Road
Otway/ Assembly hard landscape underway adjacent green room/ lobby
Acoustic panels installed top floor classrooms
Assembly stair panelling underway
Otway timber floor laid
Water fountains installed- tiling required- CVA to confirm
CL stair acoustic panels installed 2FL ceilings
Classroom 11- awaiting vertical acoustic panelling
Stair battening- awaiting acoustic panelling- classroom stairs
CL link- Praesposters court underway
TEK internal grille- RAL 9010 as wall
Security box dummy only- to be removed (not on approved drawings)
Handrail/ ramp underway to Assembly hall adjacent Ingrave Road
Ditto
Praeposters Court underway
metal profile reveals/ head flashing underway to GL A CL block
Deep reveal head flashing w/ drip- CL block
Shallow reveal head flashing w/ drip- CL block
Assembly Hall overview
Assembly hall stair cladding underway
Ditto
Curtain pocket formed AS hall
Closing piece required between fineline glazing and trench heating- now instructed
Bleachers installed
Otway tiles- to be replaced where damaged
Bleacher overview from Minstrel's gallery