23.09.16- Making good incomplete

 Decoration high level to corridor 2FL

 decoration above tiling to drinking fountain 2FL corridor

ceiling to classroom

Friday, 29 July 2016

Parapet remedials 27.07.16

 Parapet reinstated with new DPC under

 DPC projects beyond brick course as required

Hutton have introduced mortar fillet internally- not as CVA detail. However DPC is continuous under lead and into gutter

 New lead flashing to chimney

 Ditto
 Making good still to be completed out internally to soffit of classroom 15

 Current making good poorly carried out to classroom 15

 Ditto

 2nd floor corridor classroom block- making good still to be carried out

 Classroom 12- making good incomplete/ poor to ceiling- also no hatch classroom 12

 Wall finishes where previous water ingress- to be addressed/ made good classroom 12

Light fitting/ soffit to be addressed classroom 12

Tuesday, 14 June 2011

110609 Site Visit- Building Control Inspection


Light sensor to external elevation- CVA to check NEE drawings


Light sensor to external elevation- CVA to check NEE drawings


'Fire Door Keep Shut' signs to be changed to 'Fire Door Keep Clear' where operated with hold-open device


Green Fire Escape graphics still required to Push bar exits in all locations


Minstrel's gallery gate- Hasp detail to be remade to provide fixing for master gate as detail


Ditto


Mastic still required to Fineline glazing- kitemark not visible- HCL to confirm glazing fitted


'Fire Door Keep Shut' signs to be changed to 'Fire Door Keep Clear' where operated with hold-open device


Max 380mm difference between gravel fill and FFL of paving to perimeter detail Otway House


Manifestations- TBA w/ School


Benches to be fitted to low headroom areas- Manifestations not required GFL Stair 1 & 2 CL


Green Fire Escape graphics still required to Push bar exits in all locations


40mm clearance required around handrails- window lining currently obstructing


Graphics required to disabled WC alarm lights- fitted to bulkhead 1FL office CL


Bright trim still required to differentiate ramp- CL link


Kite mark required for glass to balustrade- HCL


Electromagnet hot- Action AC Leigh/ HCL