Parapet reinstated with new DPC under
DPC projects beyond brick course as required
Hutton have introduced mortar fillet internally- not as CVA detail. However DPC is continuous under lead and into gutter
New lead flashing to chimney
Ditto
Making good still to be completed out internally to soffit of classroom 15
Current making good poorly carried out to classroom 15
Ditto
2nd floor corridor classroom block- making good still to be carried out
Classroom 12- making good incomplete/ poor to ceiling- also no hatch classroom 12
Wall finishes where previous water ingress- to be addressed/ made good classroom 12
Light fitting/ soffit to be addressed classroom 12