Thursday, 29 October 2009

091029 Site Visit


Scaffolding to Otway House underway + Soakaways installation


Queens lab- background vent to be fitted


Queens lab- ducting to be installed to fume cupboard


Radiator installed- ducting decorated


Below ground service run


Below ground service run across school nears completion


Ground source heating- piling for pile No.4


Excavation for soakaway- 4 metres deep


Concrete ring for soakaway awaiting installation

Thursday, 15 October 2009

091015 Site Visit


Excavation for services across playground- discovery of Swimming Pool footings


Aerial photo of swimming pool position


Classroom footings underway


Live gas supply to corner of site


Otway ground floor- evaluate for finishes

Thursday, 8 October 2009

091007 Site visit



Footings and below ground services in progress- Classroom block



Progress of below ground services adjacent gridline 1



Progress of below ground services adjacent gridline 1




Otway brickwork verge detail- Hutton to liaise with Lambs over cost to mimic for gable end to Ingrave Road



Otway Gable end wall- new brickwork wall to follow face of existing facing brick (not chimney)



Setting out and commencement of footings to classroom block



Water ingress to Otway first floor



Water ingress to Otway first floor(2)



Removal of stair to Otway ground floor

Monday, 5 October 2009

090928 Otway Gable Wall



Otway gable end with render removed



Otway roof- and face showing standard bricks to verge detail



Gable end from inside- to be rebuilt