Thursday, 29 October 2009
091029 Site Visit
Scaffolding to Otway House underway + Soakaways installation
Queens lab- background vent to be fitted
Queens lab- ducting to be installed to fume cupboard
Radiator installed- ducting decorated
Below ground service run
Below ground service run across school nears completion
Ground source heating- piling for pile No.4
Excavation for soakaway- 4 metres deep
Concrete ring for soakaway awaiting installation
Thursday, 15 October 2009
091015 Site Visit
Thursday, 8 October 2009
091007 Site visit
Footings and below ground services in progress- Classroom block
Progress of below ground services adjacent gridline 1
Progress of below ground services adjacent gridline 1
Otway brickwork verge detail- Hutton to liaise with Lambs over cost to mimic for gable end to Ingrave Road
Otway Gable end wall- new brickwork wall to follow face of existing facing brick (not chimney)
Setting out and commencement of footings to classroom block
Water ingress to Otway first floor
Water ingress to Otway first floor(2)
Removal of stair to Otway ground floor
Monday, 5 October 2009
090928 Otway Gable Wall