Thursday, 8 October 2009
091007 Site visit
Footings and below ground services in progress- Classroom block
Progress of below ground services adjacent gridline 1
Progress of below ground services adjacent gridline 1
Otway brickwork verge detail- Hutton to liaise with Lambs over cost to mimic for gable end to Ingrave Road
Otway Gable end wall- new brickwork wall to follow face of existing facing brick (not chimney)
Setting out and commencement of footings to classroom block
Water ingress to Otway first floor
Water ingress to Otway first floor(2)
Removal of stair to Otway ground floor
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment