Monday, 30 November 2009

091126 Site visit


Classroom pattern reference panel


Classroom reference panel- Terracotta D mortar- Class 3 (Class 1 unavailable) below DPC


Footings to Assembly Hall grid line P


Preparations for rainwater pipes grid line N/18


Assembly hall footings underway grid line N


Excavation for footings to Assembly Hall gable end wall rebuild


Otway House gable end- demolition complete


Otway gable end


Classroom block grid line A/9


Detail of surface of classroom slab with irregularities


Classroom slab- typical irregularities to surface



Classroom slab- note irregularities to surface

Monday, 23 November 2009

091119 Site visit


Coloured mortars: Ibstock Heritage Red blend matched with Terracotta D
Ibstock Crowborough Multi Stock (wrong) matched with Dark Brown D- to be updated


Classroom Block- preparation for slab pour


Otway South Wing- completion of demolition


Formwork to classroom block


Continuation of reinforcement into link


Classroom reinforcement of slab


Delivery of bricks on site- crowborough incorrect!


Footings to Assembly Hall gridline M/14


Otway gable end awaiting demolition


Otway scaffold nears completion


Otway temporary support internally

Thursday, 12 November 2009

091112 Site Visit


Scaffold over Otway House nears completion


Scaffold appears in distance over Otway


MH15- Adjacent G/L Q/ 19- water backing up in drain


Plotting out edge of footing to G/L 19 in relation to below ground services


Footings cast to G/L P- excavate for downpipe


Footings cast to G/L P


Existing tile finish Otway- requires instruction to lower new boards/ carpet to match level


Scaffold internally to Otway for stair infill work


Internal partitions removed to first floor landing Otway


Internal partitions removed to first floor Otway private study


Water ingress still problematic to first floor Otway


Reinforcement to slab Classroom block progresses


Ramped area G/L A classroom block


GSHP piling continues, nearing completion


Lift pit to classroom block- setting out requires slimmer insulation between blockwork and vertical edge of concrete- internal face of pit

Thursday, 5 November 2009

091105 Site Visit


Scaffold to Otway nears completion


Drilling of Ground Source Heating Piles continues


Queens external radiuses to ducting- requiring attention


Below ground drainage/ prep for slab to classroom block


Manholes behind Allison leading to new MH 16 inspected


Assembly Hall footing G/L Q


Footings/ reinforcement G/L Q


No visible reinforcement to day joint



Preparing scaffold for lift onto Otway House