Monday, 30 November 2009
091126 Site visit
Classroom pattern reference panel
Classroom reference panel- Terracotta D mortar- Class 3 (Class 1 unavailable) below DPC
Footings to Assembly Hall grid line P
Preparations for rainwater pipes grid line N/18
Assembly hall footings underway grid line N
Excavation for footings to Assembly Hall gable end wall rebuild
Otway House gable end- demolition complete
Otway gable end
Classroom block grid line A/9
Detail of surface of classroom slab with irregularities
Classroom slab- typical irregularities to surface
Classroom slab- note irregularities to surface
Monday, 23 November 2009
091119 Site visit
Coloured mortars: Ibstock Heritage Red blend matched with Terracotta D
Ibstock Crowborough Multi Stock (wrong) matched with Dark Brown D- to be updated
Classroom Block- preparation for slab pour
Otway South Wing- completion of demolition
Formwork to classroom block
Continuation of reinforcement into link
Classroom reinforcement of slab
Delivery of bricks on site- crowborough incorrect!
Footings to Assembly Hall gridline M/14
Otway gable end awaiting demolition
Otway scaffold nears completion
Otway temporary support internally
Thursday, 12 November 2009
091112 Site Visit
Scaffold over Otway House nears completion
Scaffold appears in distance over Otway
MH15- Adjacent G/L Q/ 19- water backing up in drain
Plotting out edge of footing to G/L 19 in relation to below ground services
Footings cast to G/L P- excavate for downpipe
Footings cast to G/L P
Existing tile finish Otway- requires instruction to lower new boards/ carpet to match level
Scaffold internally to Otway for stair infill work
Internal partitions removed to first floor landing Otway
Internal partitions removed to first floor Otway private study
Water ingress still problematic to first floor Otway
Reinforcement to slab Classroom block progresses
Ramped area G/L A classroom block
GSHP piling continues, nearing completion
Lift pit to classroom block- setting out requires slimmer insulation between blockwork and vertical edge of concrete- internal face of pit
Thursday, 5 November 2009
091105 Site Visit
Scaffold to Otway nears completion
Drilling of Ground Source Heating Piles continues
Queens external radiuses to ducting- requiring attention
Below ground drainage/ prep for slab to classroom block
Manholes behind Allison leading to new MH 16 inspected
Assembly Hall footing G/L Q
Footings/ reinforcement G/L Q
No visible reinforcement to day joint
Preparing scaffold for lift onto Otway House