Thursday, 12 November 2009

091112 Site Visit


Scaffold over Otway House nears completion


Scaffold appears in distance over Otway


MH15- Adjacent G/L Q/ 19- water backing up in drain


Plotting out edge of footing to G/L 19 in relation to below ground services


Footings cast to G/L P- excavate for downpipe


Footings cast to G/L P


Existing tile finish Otway- requires instruction to lower new boards/ carpet to match level


Scaffold internally to Otway for stair infill work


Internal partitions removed to first floor landing Otway


Internal partitions removed to first floor Otway private study


Water ingress still problematic to first floor Otway


Reinforcement to slab Classroom block progresses


Ramped area G/L A classroom block


GSHP piling continues, nearing completion


Lift pit to classroom block- setting out requires slimmer insulation between blockwork and vertical edge of concrete- internal face of pit