Thursday, 12 November 2009
091112 Site Visit
Scaffold over Otway House nears completion
Scaffold appears in distance over Otway
MH15- Adjacent G/L Q/ 19- water backing up in drain
Plotting out edge of footing to G/L 19 in relation to below ground services
Footings cast to G/L P- excavate for downpipe
Footings cast to G/L P
Existing tile finish Otway- requires instruction to lower new boards/ carpet to match level
Scaffold internally to Otway for stair infill work
Internal partitions removed to first floor landing Otway
Internal partitions removed to first floor Otway private study
Water ingress still problematic to first floor Otway
Reinforcement to slab Classroom block progresses
Ramped area G/L A classroom block
GSHP piling continues, nearing completion
Lift pit to classroom block- setting out requires slimmer insulation between blockwork and vertical edge of concrete- internal face of pit