Thursday, 25 February 2010
100225 Site Visit
TSI Structural frame perimeter details
Precast stairs installed
Precast stairs
Omnia installed for first floor classroom block
Plinth steel assembly hall nears completion
Otway Lunette damage
Otway arch damage
Omnia birdsmouth detail- underside of slab
Junction of stair- minimal tolerance
Otway chimney A- prep for removal
Otway basement- flooding still apparent
Perimeter detail complete adjacent courtyard
Wednesday, 24 February 2010
100223 Site Visit
Thursday, 18 February 2010
100218 Site Visit
Steel frame to Assembly Hall nears completion
View of end elevation of Steel frame
Internal view of frame- to fixed tiered seating area
Fixed tiered seating above, recess for retractable bleachers below
Opening to fixed balustrade frame
Opening to courtyard from hall
Link to Otway house
View from courtyard
Final roof elements being installed
extra leg to baseplate G/L P/Q/ 14
Link element roof
Assembly hall and Allison block
Brickwork to Otway ground floor opening requires attention
Blockwork to classroom block G/L A 4-6 requires attention
Blockwork to classroom block G/L A 4-6 requires attention
Soft red brick damaged following removal of render to Otway entrance Ingrave Road GFL
Allison roof tiles damaged adjacent site
Friday, 12 February 2010
100211 Site Visit
Chimney to GL I/10 requires repair
Erosion to pointing
Weather damage to chimney
Rebuild of upper part suggested
Chimney overview
OT.EW.00.10 arch
OT.EW.00.11 arch w/ existing services penetration
Classroom brick pattern with brick light left
Blockwork to classroom GL C/1
Classroom CL.EW.00.18
CL.00.03 window opening now added
CL.00.04- window opening now added
Block and facing brick continues GFL Classroom block
Assembly Hall Steel frame erection commences
Steel frame Assembly Hall
Roof steels
Steel frame erection sequence- overview