Monday, 8 February 2010
100204 Site Visit
Ibstock Bevern Dark- Some bricks still with damaged faces
Ground floor courtyard elevation of classroom block
DPC detail- projecting 5mm either side
Pattern brickwork underway
DPC bonding issue resolved with insulation
Kingspan insulation installed
Lift shaft block underway
DPC peeling away due to cold weather
Class 1 mortar used to blockwork
Openings formed
Temporary support to Otway ground floor
Flooding continues in Otway basement
Assembly Hall slab completed
trough formed to assembly hall slab