Tuesday, 14 June 2011

110609 Site Visit- Building Control Inspection


Light sensor to external elevation- CVA to check NEE drawings


Light sensor to external elevation- CVA to check NEE drawings


'Fire Door Keep Shut' signs to be changed to 'Fire Door Keep Clear' where operated with hold-open device


Green Fire Escape graphics still required to Push bar exits in all locations


Minstrel's gallery gate- Hasp detail to be remade to provide fixing for master gate as detail


Ditto


Mastic still required to Fineline glazing- kitemark not visible- HCL to confirm glazing fitted


'Fire Door Keep Shut' signs to be changed to 'Fire Door Keep Clear' where operated with hold-open device


Max 380mm difference between gravel fill and FFL of paving to perimeter detail Otway House


Manifestations- TBA w/ School


Benches to be fitted to low headroom areas- Manifestations not required GFL Stair 1 & 2 CL


Green Fire Escape graphics still required to Push bar exits in all locations


40mm clearance required around handrails- window lining currently obstructing


Graphics required to disabled WC alarm lights- fitted to bulkhead 1FL office CL


Bright trim still required to differentiate ramp- CL link


Kite mark required for glass to balustrade- HCL


Electromagnet hot- Action AC Leigh/ HCL

Monday, 6 June 2011

Friday, 20 May 2011

110519 Site Visit


Footings to courtyard landscape walls


Cleaning to classroom brickwork still required


Classroom ground floor snagging


Assembly stair- handrail installation


CVA condemn Otway/ Assembly Junckers floor transition- 10mm discrepancy. HCL to now address


Otway perimeter landscape walls underway


Damp patch to Otway wall- not improving.


CL stair 1


Brick lights- issue regarding size- CVA to liaise with MFLLP regarding spec.


CL stair 1 soffit/ trim installed


Stair 2 nearing completion- final lacquer required


Gates to Ingrave Road re-installed


Soft landscape works ongoing to Ingrave Road side


Air test underway assembly hall


Praeposters/ tile transitions general to be address


Lean-to greenhouse removed


footings adjacent Queens


Greenhouse slab poured


Draw pit to be repositioned- current conflict with hard/ soft landscape transitions


Courtyard landscape underway- levels raised


Brickwork to be cleaned- classroom block


Landscape- courtyard


Gas pipes- CVA to check with MFLLP whether these can be grey as currently conspicuous


Soft landscape Ingrave Road


Otway/ Assembly overview


Landscape lighting- base to go on base course- top fitting to be masked to maintain access when final coat (resin-bound) is applied


Assembly green room lighting does not match specified fitting- HCL to advise