Tuesday, 14 June 2011
110609 Site Visit- Building Control Inspection
Light sensor to external elevation- CVA to check NEE drawings
Light sensor to external elevation- CVA to check NEE drawings
'Fire Door Keep Shut' signs to be changed to 'Fire Door Keep Clear' where operated with hold-open device
Green Fire Escape graphics still required to Push bar exits in all locations
Minstrel's gallery gate- Hasp detail to be remade to provide fixing for master gate as detail
Ditto
Mastic still required to Fineline glazing- kitemark not visible- HCL to confirm glazing fitted
'Fire Door Keep Shut' signs to be changed to 'Fire Door Keep Clear' where operated with hold-open device
Max 380mm difference between gravel fill and FFL of paving to perimeter detail Otway House
Manifestations- TBA w/ School
Benches to be fitted to low headroom areas- Manifestations not required GFL Stair 1 & 2 CL
Green Fire Escape graphics still required to Push bar exits in all locations
40mm clearance required around handrails- window lining currently obstructing
Graphics required to disabled WC alarm lights- fitted to bulkhead 1FL office CL
Bright trim still required to differentiate ramp- CL link
Kite mark required for glass to balustrade- HCL
Electromagnet hot- Action AC Leigh/ HCL
Monday, 6 June 2011
Friday, 20 May 2011
110519 Site Visit
Footings to courtyard landscape walls
Cleaning to classroom brickwork still required
Classroom ground floor snagging
Assembly stair- handrail installation
CVA condemn Otway/ Assembly Junckers floor transition- 10mm discrepancy. HCL to now address
Otway perimeter landscape walls underway
Damp patch to Otway wall- not improving.
CL stair 1
Brick lights- issue regarding size- CVA to liaise with MFLLP regarding spec.
CL stair 1 soffit/ trim installed
Stair 2 nearing completion- final lacquer required
Gates to Ingrave Road re-installed
Soft landscape works ongoing to Ingrave Road side
Air test underway assembly hall
Praeposters/ tile transitions general to be address
Lean-to greenhouse removed
footings adjacent Queens
Greenhouse slab poured
Draw pit to be repositioned- current conflict with hard/ soft landscape transitions
Courtyard landscape underway- levels raised
Brickwork to be cleaned- classroom block
Landscape- courtyard
Gas pipes- CVA to check with MFLLP whether these can be grey as currently conspicuous
Soft landscape Ingrave Road
Otway/ Assembly overview
Landscape lighting- base to go on base course- top fitting to be masked to maintain access when final coat (resin-bound) is applied
Assembly green room lighting does not match specified fitting- HCL to advise