110519 Site Visit


Footings to courtyard landscape walls


Cleaning to classroom brickwork still required


Classroom ground floor snagging


Assembly stair- handrail installation


CVA condemn Otway/ Assembly Junckers floor transition- 10mm discrepancy. HCL to now address


Otway perimeter landscape walls underway


Damp patch to Otway wall- not improving.


CL stair 1


Brick lights- issue regarding size- CVA to liaise with MFLLP regarding spec.


CL stair 1 soffit/ trim installed


Stair 2 nearing completion- final lacquer required


Gates to Ingrave Road re-installed


Soft landscape works ongoing to Ingrave Road side


Air test underway assembly hall


Praeposters/ tile transitions general to be address


Lean-to greenhouse removed


footings adjacent Queens


Greenhouse slab poured


Draw pit to be repositioned- current conflict with hard/ soft landscape transitions


Courtyard landscape underway- levels raised


Brickwork to be cleaned- classroom block


Landscape- courtyard


Gas pipes- CVA to check with MFLLP whether these can be grey as currently conspicuous


Soft landscape Ingrave Road


Otway/ Assembly overview


Landscape lighting- base to go on base course- top fitting to be masked to maintain access when final coat (resin-bound) is applied


Assembly green room lighting does not match specified fitting- HCL to advise