Friday, 20 May 2011
110519 Site Visit
Footings to courtyard landscape walls
Cleaning to classroom brickwork still required
Classroom ground floor snagging
Assembly stair- handrail installation
CVA condemn Otway/ Assembly Junckers floor transition- 10mm discrepancy. HCL to now address
Otway perimeter landscape walls underway
Damp patch to Otway wall- not improving.
CL stair 1
Brick lights- issue regarding size- CVA to liaise with MFLLP regarding spec.
CL stair 1 soffit/ trim installed
Stair 2 nearing completion- final lacquer required
Gates to Ingrave Road re-installed
Soft landscape works ongoing to Ingrave Road side
Air test underway assembly hall
Praeposters/ tile transitions general to be address
Lean-to greenhouse removed
footings adjacent Queens
Greenhouse slab poured
Draw pit to be repositioned- current conflict with hard/ soft landscape transitions
Courtyard landscape underway- levels raised
Brickwork to be cleaned- classroom block
Landscape- courtyard
Gas pipes- CVA to check with MFLLP whether these can be grey as currently conspicuous
Soft landscape Ingrave Road
Otway/ Assembly overview
Landscape lighting- base to go on base course- top fitting to be masked to maintain access when final coat (resin-bound) is applied
Assembly green room lighting does not match specified fitting- HCL to advise