Monday, 16 May 2011

110512+13 Site Visit


Ingrave Road overview: Landscape base course laid/ kerbs installed


AS- harbo panelling installed- spindles for Salto too short- consult AC Leigh


AS- acoustic panel frames decorated


AS- stair nosing detail/ inset tread


AS- stair overview


CL- handrail to stair 2 underway- sweeping bends resolved


CL- stair 1- handrail completed- awaiting lacquer


CL- matwell installed


OT- perimeter landscape wall underway


CL- stair 1- infill panel to acoustic ceiling required GFL


Otway stair- lighting installed/ decs almost complete


CL- stair 1- alternative escape light required- CVA/ MFLLP to discuss


OT/AS- discrepancy in floor finish levels in transition- HCL to advise/ propose solution


Otway arch- 2 No. repairs required


AS- plinth landscape capping complete- awaiting block pavers/ manholes


ditto


AS- soft landscape to perimeter underway


Minor additional repointing required to Ingrave Road wall


Tree stumps- to be grubbed/ removed


AS- awaiting soffit panels


Praeposters court- hard landscape complete- Otway door decoration required


GEN: Window linings generally require rub down/ redec.


GFL classroom 1- grilles installed- making good/ redec required


CL stair panels installed Stair


Green room- flashing required for return glazing


AS plant room- repair to damaged brickwork required


AS_ plinth completed- awaiting resin bound gravel final coat


PR- courtyard landscape footings underway