110426 + 28 Site Visit


Classroom block overview


AS lobby door floor springs


... require alignment


mistakenly fitted with hinges previously- lipping must be replaced.


Slot drain to AS lobby exit doors


AS Plant Room grille treatment required


Green room cill/ wall to be completed


Soft joint required to AS green room


ditto + brick inset and trim off profile


Otway- typical items to wall still requiring removal


Moss requiring removal to Otway walls


Praeposters Court nearing completion- awaiting tile to threshold


Cables/ staples typically requiring removal- Otway


Window profiles sagging in some locations


Brick repairs required high level- CL


Pointing still requires attention CL chimney adjacent Queens


CL canopy carpentry underway- awaiting Bauder roof


Brick lights- installation required


Trickle vents/ grilles omitted in some locations CL


AS stair ply panelling unprotected/ damaged


Otway perimeter fixed benching installed- grille detail


AS soffitt profiles- poorly installed- to be redone


Classroom 11 CL- lighting installed incorrectly


Classroom 11- Acoustic panels installed incorrectly + cover profile omitted


AS bulkhead to hall misaligned- to be redone


Head of Praes court door/ ceiling misaligned


HTP benching on site


Door closer to CL stair 2- clearance to Stair 1 problem when installed


MDF linings to CL windows poorly finished


CL corridor finishes generally- require areas to be made good to perimeter/ around hatches/ light fittings


CL classroom making good generally required around light fittings


CL covers- installation still required classroom 16


Classroom 12- light fitting poorly installed- to be redone


Ditto


Removed trees- stump significant- to be cut done where permitted


AS escape door cover panel poorly installed- to be redone


ditto


Escape door overview


Ingrave Road wall- patching in of marked up bricks


Repointed wall completed