Wednesday, 11 May 2011

110505 + 09 Site Visit


Courtyard overview- site being cleared


Ingrave Road- Landscaping well underway inc. asphalt base coat


Typical snagging 2fl- making good switches


Typical snagging 2fl- mastic adjacent cill/ grille to window


Typical snagging 2fl- ceiling make good/ patch/ fill/ redecorate where necessary


Stair 1- intumescent lacquer- base coat


Handrails underway stair 1


Acoustic panels- snagging to some areas Stair 1


Assembly- Harbo panelling nearing completion


Ditto


Tree trunks- further cutting required


Stair 2- acoustic panelling underway


Link- pattern tiling uncovered


Assembly stair- Junckers underway


AS.ID.01.02- Salto ironmongery incorrect


Brickwork still to be cleaned in a number of areas- classroom block- HCL to advise





Harbo panelling/ lighting to assembly hall


bulkhead to piano store


Piano store panelling- ceiling at wrong level/ panelling notched- HCL to advise


Junckers underway to assembly hall lobby


Ingrave Road landscaping underway


Wall repointed Ingrave Road


Otway link door on hold open


Mastic to plant grille perimeter- Action HCL- now scheduled on PR513