Wednesday, 11 May 2011
110505 + 09 Site Visit
Courtyard overview- site being cleared
Ingrave Road- Landscaping well underway inc. asphalt base coat
Typical snagging 2fl- making good switches
Typical snagging 2fl- mastic adjacent cill/ grille to window
Typical snagging 2fl- ceiling make good/ patch/ fill/ redecorate where necessary
Stair 1- intumescent lacquer- base coat
Handrails underway stair 1
Acoustic panels- snagging to some areas Stair 1
Assembly- Harbo panelling nearing completion
Ditto
Tree trunks- further cutting required
Stair 2- acoustic panelling underway
Link- pattern tiling uncovered
Assembly stair- Junckers underway
AS.ID.01.02- Salto ironmongery incorrect
Brickwork still to be cleaned in a number of areas- classroom block- HCL to advise
Harbo panelling/ lighting to assembly hall
bulkhead to piano store
Piano store panelling- ceiling at wrong level/ panelling notched- HCL to advise
Junckers underway to assembly hall lobby
Ingrave Road landscaping underway
Wall repointed Ingrave Road
Otway link door on hold open
Mastic to plant grille perimeter- Action HCL- now scheduled on PR513
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment