Steel installed Otway GL I

Chimney brickwork paused- awaiting installation of roof panels

Gutter awaiting overflow- HCL to advise regarding rigid insulation between parapet and gutter

Kingspan KTS 1000 panels installed GL 9

Assembly hall plinth overview

Chimney/ ringbeam cutting underway

DGT gutter GL 1- aluminium leg to gutter too high in relation to parapet- HCL to advise

Gutter GL 1

HRW to review lintel calcs- minor crack to mortar GL C brickwork 1FL

Thermal bridge- chimney base cast incorrectly- details revised accordingly to eliminate

Roofscape overview from Assembly- Otway valley rooflights now fitted

Ball guards now installed Assembly Hall

South Elev brickwork assembly- GL Q

GL Q/ 16 high level parapet relief work

GL 14 brickwork now underway

Assembly hall ceiling installed inc. drop rods- + mist coat

Classroom 11 awaiting internal chimney/ roof panels

Classroom link- floor deck installed

ditto

View of Assembly Hall from Praes