Assembly ductwork underway
sequence
ditto
ditto
top hat sections installed GL Q- awaiting lining
Plaster to GFL classrooms- w/ termination bead and contraction joint completed
1st fix elec for lighting/ plastering to WCs GFL classroom
Containment query GFL classroom s- CVA/ HCL to liaise
expamet to blockwork where changes in substrate
Fireline to GFL Otway
ditto- + 1st fix elec
prep for light fitting to GFL stair 1
Otway dry-fix ridge tile- mortar poor finish
ditto
MFLLP to confirm omission of 1 No. light fitting stair 1 1st floor

TEK vent/ grille installed- protective galv cill

ditto

Fire stopping to doorways- classroom block

Classroom block gable end overview

Brickwork damaged by scaffold GL A

ditto

TEK vent external view

GL A overview external or openings

GLQ/18- additional support req'd- CVA to instruct/ advise

Top hat sections fixed GL Q internal

ditto

Brickwork GL 14

Brickwork GL Q external

Gables- geometry high level

Acoustic/ stopping required Assembly plenum

Additional bolts required to steel connection

Intumescent paint req'd to classroom link
CL.01.18 internal reveal too low- HCL to advise