| High level brickwork at Assembly Hall approach completion with first gables being finished. |
| Lintol to first floor link between Otway and Assembly to be installed. |
| High level ceiling lining to Otway existing structure in first floor lobby. Suspended ceiling to be added. |
| Hutton to ensure that refurbished existing plaster to be brought back to provide a good key for new plaster. |
| Final lining to high level Otway ceiling being installed to ensure clean junctions around roof form. |
| High level exposed roof structure with lining to roof. Area above stair insulated without plasterboard given suspended ceiling below. |
| Hutton to finish plasterboard lining above PFC with neat beading detail. |
| Skimming to refurbished ground floor soffit in Otway largely complete. Suspended acoustic ceiling to follow. |
| Services through main Otway riser to first floor. |
| Existing cornice timber supports in Otway to be stripped out and plaster made good. |
| Pipework installed prior to completion of plasterboard. If bulkhead cannot be made to perform in an acceptable acoustic/fire performance, Hutton must propose remedial solution. |
| Two options for additional new bricks to Otway to match existing. Brick on top agreed to be the best match. |
| Route of rainwater downpipe in link at the external wall of Otway to be resolved. |
| Work to restore triple arch in Otway with new Lambs bricks underway. |
| Completed Assembly Hall gable. |
| Site dimension confirming capping size is correct. Internal lining to parapet to be resolved. |
| Internal lining to Assembly Hall underway. |
| Screed to ancilliary spaces of Assembly along Ingrave Road poured to 50mm below FFL. Additional screed or unobat system required to achieve FFL. |
| Junction of Mezzanine at External wall of Assembly. Issue of structural design to be resolved. |
| Hutton to issue Taylor Engineering proposal for supporting internal wall linings. |
| Support to Assembly mezzanine around RWP needs to be resolved |
| Plastering to Classrooms ongoing |
| Acoustic and thermal linings to Classroom chimneys and also structural straps underway. |
| Rainwater outlets to Classroom, internally routed from gutter largely complete. |
| Rooflights installed from within 2F classroom. |
| Hip of roof discussed on site with view to omit ventilated tiles. |
| Damage to roofing panels, roofer to advise on edge of tiling over gutter. |
| rooflights installed, fixed to timber bolted down to steelwork below. lead flashing below, awaiting aluminium soaker/upstands to complete flashing. |
| Row of rooflights installed along Classroom roof, once tiling is on these will be flush with the roof finish. |
| Area of roof valley where it is proposed to move SVPs. |
| View of patterned Assembly brick from Ingrave Road. |