DGT gutter works/ interface require additional work GL D/1

DGT/ HCL to advise over quality of hip formed GL B/1

Ditto

Flashings/ rooflights underway Classroom block GL C

Trapezoid rooflight frame installation underway GL4

Underside of trapezoid rooflight

Otway query- upper sash fixed/ sealed? CVA to confirm

CVA to confirm fire-lining of ceiling/ duct where ceiling not continuous

Gable end arch replacement underway

OT.EW.01.03- arch specified to be reused not retained. HCL to forward quote for replacement asap.

Otway linings near completion to loft

Scaffold to arch- Otway gable end

Classroom roof panels installed

Link roof carpentry complete

Riser 1- CVA to clarify boiler flue penetration

Plantroom classroom block- CVA to clarify fire-stopping/ acoustic seal

Contraction joint to blockwork- plaster detail- classroom block GFL corridor

Site painting- acoustic louvre- TEK completed

Soffit GFL- condensation throughout- CVA to monitor

Special bricks to lintel- assembly hall GL 18

Brickwork to gables complete- GL Q

Brickwork GL Q

Concrete fill to be completed- GL 14

GL L/14 parapet nearing completion

Confirmation required to internal lining support- 1st floor assembly

Linings to assembly hall nearing completion- CVA to confirm low level air-tightness

High level ducts installed

Linings assembly hall

ditto

door linings to assembly lobby

fan coil unit to assembly toilet soffit

Penetrations for light fittings to assembly- HCL to ensure good seal around fittings when installed