Thursday, 7 April 2011

110405/06/07 Site Visit


Classroom link sedum installed


Otway pelmet installed


CVA to review junction/ decs to pelmet


Otway large pendant lighting installed


Assembly overview


Recess formed for lighting to green room


mini-bulkhead to assembly stair required as detail


ditto


Otway pelmet/ lighting


Classroom link GFL


Classroom Stair 2 lining underway


Assembly hall/ Otway overview


Classroom landscape/ road underway


Assembly Sedum blanket installed


Assembly/ Otway interface complete- soft joint required under steel adjacent door head


CVA to liaise with fineline regarding infill trim


Assembly timber floor installation underway


Fixed tiered seating installed 1st floor


Tek cover grilles on site awaiting installation


AS escape doors