Thursday, 7 April 2011
110405/06/07 Site Visit
Classroom link sedum installed
Otway pelmet installed
CVA to review junction/ decs to pelmet
Otway large pendant lighting installed
Assembly overview
Recess formed for lighting to green room
mini-bulkhead to assembly stair required as detail
ditto
Otway pelmet/ lighting
Classroom link GFL
Classroom Stair 2 lining underway
Assembly hall/ Otway overview
Classroom landscape/ road underway
Assembly Sedum blanket installed
Assembly/ Otway interface complete- soft joint required under steel adjacent door head
CVA to liaise with fineline regarding infill trim
Assembly timber floor installation underway
Fixed tiered seating installed 1st floor
Tek cover grilles on site awaiting installation
AS escape doors