Friday, 1 April 2011

110330+31 Site Visit


Assembly subfloor installation underway


Otway scaffold struck, final brick repairs underway


Fineline doors installed, Junkers underway internally


Punkah fans installed Otway


Hatch/ linings installed AS stair lobby


Beech cladding underway stair 2 classroom block


Steel canopy to classroom underway


Green room glazing complete


Ditto


Classroom block overview


Assembly Hall overview


Glass-to-glass corner- green room


AS stair linings underway


CL stair 1 linings nearing completion- sanding/ filling/ lacquering/ capping to follow


Classroom 12 decorations near completion


Fixed tiered seating platform


trench heating installed Assembly hall


1st stage acoustic panels installed


projector space- awaiting perforate panel


Mistrel's gallery- lighting setting out to adjust around rwp