110324 Site Visit


Green room glazing underway


Stair 1 lining underway


Top floor classroom decoration


Closing piece to curtain wall, classroom link GFL


Otway teapoint joinery complete


lining details forwarded to HCL for rooflight


Fixed joinery underway to 1fl careers library- CL link


Otway pastoral offices nearing completion 1FL


Latchway system underway to AS plinth roof


1FL Assembly link trench heating installed


CVA to confirm updated setting out around RWP.AS.08


AS stair glazing complete- awaiting linings


AS link


Classroom block- scaffold struck to link


AS GFL glazing to plinth nearing completion


Acoustic panel housing installed AS high level hall


AS link external- awaiting soffit panels


Fineline/ trench heating


AS link overview


Cracks over GL C CL.EW.00.14- monitor- HCL to repoint


Ditto