110324 Site Visit
Green room glazing underway
Stair 1 lining underway
Top floor classroom decoration
Closing piece to curtain wall, classroom link GFL
Otway teapoint joinery complete
lining details forwarded to HCL for rooflight
Fixed joinery underway to 1fl careers library- CL link
Otway pastoral offices nearing completion 1FL
Latchway system underway to AS plinth roof
1FL Assembly link trench heating installed
CVA to confirm updated setting out around RWP.AS.08
AS stair glazing complete- awaiting linings
AS link
Classroom block- scaffold struck to link
AS GFL glazing to plinth nearing completion
Acoustic panel housing installed AS high level hall
AS link external- awaiting soffit panels
Fineline/ trench heating
AS link overview
Cracks over GL C CL.EW.00.14- monitor- HCL to repoint
Ditto