Monday, 14 March 2011
100310 Site Visit
Lighting fitted to pelmet area Otway
Classroom roof tiling underway GL D/4
Classroom tiling
Fineline AS installation underway GFL
CVA to confirm setting out of cheeks to CL.RL.03.02
Ceiling underway Classroom 12 2fl
Bauder underway to AS plinth roof
Ditto
Fireborn capping end requires Epoxy filler to extrusion or custom end cap- HCL to investigate
Outlet to AS plinth- HCL to set out- tight in relation to steelwork/ parapet
Panelling to AS staging- CVA to amend to accommodate RWP position which differs from proposed
Framing underway for AS acoustic panelling
Awaiting soffit panels
Omitted motif added AS plinth Ingrave Road GL 20
Acoustic plantroom doors added
landscape details underway adjacent assembly
Cupboard high level- leads to be fed through top- Otway teapoint area
Assembly stair steel/ timber underway- additional steel required
Ditto
High level assembly hall- services clash. Stage Electrics/ NEE to resolve
Brickwork GL 14
Brickwork AS gridline 14
Otway interior 1FL
Classroom Block- roofing to GL D
Handrail required to CL link- CVA to forward
MF frame lowered 1FL ICT classroom for flush light fitting
Factory cut edge now facing bulkhead as required- flush with finish of bulkhead vertical face
Flashing piece to grilles reuired- CL 2FL plantroom
Radius now skimmed- 2FL classrooms
Classroom link parapet underway
Classroom 12 ceiling underway
Framing to GFL CL link underway in prep for glazed screen
CL toilets- film required to fanlight high level
Hatches to CL acoustic bulkheads- holes aligned/ complete