Friday, 18 March 2011

100317 Site Visit


Ingrave Road- overview with scaffold struck


Assembly Hall- windows installed 1st flr


AS- Fineline glazing installation underway to courtyard


CL link- curtain walling installation nearing completion


discrepancy to head/ cill- HCL to liaise with SecCo regarding interface with soffitt panels


Awaiting soffitt panel to reveal for completion- classroom north elevation


Classroom block-Library square overview


Assembly link- awaiting Fineline glass installation


Assembly interior- acoustic reflector panel installation nearing completion


CL stairs- tiling underway with contrasting nosing/ riser detail


Ditto


Classroom 12 lining complete- awaiting joinery


Classroom 16- window reveal complete


Classroom 16 - ceiling awaiting bead/ skim


Joinery scalloped pen rest detail to whiteboards


Overview


CL roof- adjustment required to trapezoid rooflight tiling perimeter


CL gambrel- detail not as drawn- to be reworked

Ditto- flashing girth to be greater/ no intermediate tile to transition


OT- Sealant to 1fl windows complete except OT.EW.01.08


Fineline rail overlooking plinth roof


Sleeve around hot pipes installed


Gulley installed to AS plinth


CVA/ HRW to forward guarding details- AS mezzanine- RHS


CVA/ HRW to forward guarding details- AS mezzanine- LHS


Central aisle cavity- for gate- CVA/ HRW to forward details


CVA to forward handrail details AS mezzanine


TEK vent to green room installed


External view- TEK green room vent


Glazing underway - AS green room


AS panelling frame nears completion


AS ceiling


AS Reflectors


AS court overview


HTP sample client supply locker delivered to staff room
WISA to match other joinery