Friday, 18 March 2011
100317 Site Visit
Ingrave Road- overview with scaffold struck
Assembly Hall- windows installed 1st flr
AS- Fineline glazing installation underway to courtyard
CL link- curtain walling installation nearing completion
discrepancy to head/ cill- HCL to liaise with SecCo regarding interface with soffitt panels
Awaiting soffitt panel to reveal for completion- classroom north elevation
Classroom block-Library square overview
Assembly link- awaiting Fineline glass installation
Assembly interior- acoustic reflector panel installation nearing completion
CL stairs- tiling underway with contrasting nosing/ riser detail
Ditto
Classroom 12 lining complete- awaiting joinery
Classroom 16- window reveal complete
Classroom 16 - ceiling awaiting bead/ skim
Joinery scalloped pen rest detail to whiteboards
Overview
CL roof- adjustment required to trapezoid rooflight tiling perimeter
CL gambrel- detail not as drawn- to be reworked
Ditto- flashing girth to be greater/ no intermediate tile to transition
OT- Sealant to 1fl windows complete except OT.EW.01.08
Fineline rail overlooking plinth roof
Sleeve around hot pipes installed
Gulley installed to AS plinth
CVA/ HRW to forward guarding details- AS mezzanine- RHS
CVA/ HRW to forward guarding details- AS mezzanine- LHS
Central aisle cavity- for gate- CVA/ HRW to forward details
CVA to forward handrail details AS mezzanine
TEK vent to green room installed
External view- TEK green room vent
Glazing underway - AS green room
AS panelling frame nears completion
AS ceiling
AS Reflectors
AS court overview
HTP sample client supply locker delivered to staff room
WISA to match other joinery