Chimney rebuild/ scaffold to Otway. Chimney pots/ caps to be added


Terracotta transoms to be installed- details to be discussed/ confirmed.


Lambs terracotta sections


Steel strap required to arch AS.ID.01.01


Corbelling of brickwork required to meet chimney size above


Valley timber to be uncovered to reveal if any further rot present


Assembly high level reference panel complete- but comments from previous SVR still unresolved regarding alignment/ specials/ cuts. To be addressed.


Crack to slab 2nd floor G/L B 1-2


Crack- detail


Junction GL C/4


2nd floor slab after pour


Assembly hall blockwork GL N/20


Assembly Hall blockwork underway


Blockwork adjacent steelwork supporting mezzanine- awaiting intumescent paint


Blockwork/ DPC forming trench/ plenum to assembly hall


Penetrations of blockwork will now require intumescent silicon seal


Windows/ Metsec set out assembly hall


Metsec to assembly hall


Framing out of roof complete to assembly hall high level roof


Insulation/ framing out complete to some areas in assembly hall


Blockwork infill underway to assembly hall ground floor level