Monday, 10 May 2010
100506 Site Visit
Chimney rebuild/ scaffold to Otway. Chimney pots/ caps to be added
Terracotta transoms to be installed- details to be discussed/ confirmed.
Lambs terracotta sections
Steel strap required to arch AS.ID.01.01
Corbelling of brickwork required to meet chimney size above
Valley timber to be uncovered to reveal if any further rot present
Assembly high level reference panel complete- but comments from previous SVR still unresolved regarding alignment/ specials/ cuts. To be addressed.
Crack to slab 2nd floor G/L B 1-2
Crack- detail
Junction GL C/4
2nd floor slab after pour
Assembly hall blockwork GL N/20
Assembly Hall blockwork underway
Blockwork adjacent steelwork supporting mezzanine- awaiting intumescent paint
Blockwork/ DPC forming trench/ plenum to assembly hall
Penetrations of blockwork will now require intumescent silicon seal
Windows/ Metsec set out assembly hall
Metsec to assembly hall
Framing out of roof complete to assembly hall high level roof
Insulation/ framing out complete to some areas in assembly hall
Blockwork infill underway to assembly hall ground floor level