Monday, 17 May 2010

100513 Site Visit


Assembly hall- gutter being installed to high level roof by DGT


Assembly Hall- Metsec/ insulation nearing completion to walls


Gutter being installed GL Q/16


Gutter installed GL P/18


Minstrel's Gallery- control room awaiting penetrations within floor/ trimming steels


Hutton mark up discrepancies within Assembly Hall high level reference panel


Gutter/ outlet position GL Q/16. Outlet positions not generally as drawn. HUT to review all positions/ downpipe connections


Outlet/ gutter GL Q/18


Outlet GL Q/14- clash between plate and downpipe


Minstrel's Gallery- progress to Metsec/ insulation/ roof deck


Detail/ COI required for local areas over door to courtyard- Assembly Hall


Roof gutters in progress


Window openings formed in Metsec


Blockwork GFL complete Assembly hall plinth area


Gaps maintained for Intumescent treatment


Classroom 2nd floor slab- more localised cracking GL A-B/1-2


Beam cast GL 2-3/C-D


Blockwork underway 2nd floor classroom block


Precast stair 1st to 2nd floor installed


Lintel installed Otway GL G 1st Floor


Setting out amended to partial height wall GL H


Steel beam taking Chimney C


Steel/ valley beam exposed


Openings formed- partial height walls around Otway stair


Tie exposed to existing wall GL I/11 1st floor- Hutton to propose casting in to padstone


Classroom block- pointing discoloured GL 1 chimney