100520 Site Visit


Site overview from Ingrave Road- Classroom block


Site overview from Ingrave Road- Otway/ Assembly Hall


Interface between steel/ block- awaiting intumescent


Ditto- int. mastic required to joint


Plywood/ tek screws discussed for brickwork support to steel low level opening


Gutters/ ply deck in progress


Gutters- DGT to provide support/ calcs for rainwater


Corner gutter- support under to be clarified by DGT


Strap detail to high level roof perimeter


Overview of gables assembly hall


Flaunching- review method to deal with cracking


Flaunching to be redone where pots replaced


Gable end Otway timbers


Ditto


Arch repair Otway


Ditto


Brick repair- mortar colour to be reviewed/ discussed further with conservation officer 25.05.10


mortar to rebuilt chimney


Openings formed 1st floor Otway


Steel downstand beams to Teapoint GFL- CVA to review removal


Beams above- 3 No. timber joists requiring replacement if steels removed


Blockwork Classroom 2FL- proceeding


Reveal detail incorrect- to be modified to allow for differential movement of internal and external skins


Ditto


Edge beam GL D/1


GL D/3- edge detail discrepancy still to be confirmed


Possible knotweed plant adjacent substation