Monday, 24 May 2010
100520 Site Visit
Site overview from Ingrave Road- Classroom block
Site overview from Ingrave Road- Otway/ Assembly Hall
Interface between steel/ block- awaiting intumescent
Ditto- int. mastic required to joint
Plywood/ tek screws discussed for brickwork support to steel low level opening
Gutters/ ply deck in progress
Gutters- DGT to provide support/ calcs for rainwater
Corner gutter- support under to be clarified by DGT
Strap detail to high level roof perimeter
Overview of gables assembly hall
Flaunching- review method to deal with cracking
Flaunching to be redone where pots replaced
Gable end Otway timbers
Ditto
Arch repair Otway
Ditto
Brick repair- mortar colour to be reviewed/ discussed further with conservation officer 25.05.10
mortar to rebuilt chimney
Openings formed 1st floor Otway
Steel downstand beams to Teapoint GFL- CVA to review removal
Beams above- 3 No. timber joists requiring replacement if steels removed
Blockwork Classroom 2FL- proceeding
Reveal detail incorrect- to be modified to allow for differential movement of internal and external skins
Ditto
Edge beam GL D/1
GL D/3- edge detail discrepancy still to be confirmed
Possible knotweed plant adjacent substation