Tuesday, 8 June 2010
100603 Site Visit
Assembly Hall 1st fix mechanical commences
Penetration to WC
1st fix mechanical under mezzanine
Pipework to drama store/ side stage
DGT roofing- profile awaiting cut to allow for windpost detail
Roof panel installation
Awaiting brickwork low level- assembly hall plinth
High level blockwork 2fl classroom
Additional detail required to classroom deep reveals 2fl
Otway- Teapoint beams now removed
Chimney- scaffold removed
Assembly Hall high level reference panel- reviewed following modifications
View in conjunction with reference panel mark-ups
Mortar shallow
Pattern not aligned
Pointing inconsistent
Pointing inconsistent
Assembly Hall low level reference panel- reviewed following modifications
Omit contrasting pointing
As left hand side
Pointing to be more precise where contrasting
Omit additional red brick between motifs
Contrasting pointing to be clearly distinguished
DPC to be cut in Classroom brick (sample shown)