Tuesday, 8 June 2010

100603 Site Visit


Assembly Hall 1st fix mechanical commences


Penetration to WC


1st fix mechanical under mezzanine


Pipework to drama store/ side stage


DGT roofing- profile awaiting cut to allow for windpost detail


Roof panel installation


Awaiting brickwork low level- assembly hall plinth


High level blockwork 2fl classroom


Additional detail required to classroom deep reveals 2fl


Otway- Teapoint beams now removed


Chimney- scaffold removed


Assembly Hall high level reference panel- reviewed following modifications
View in conjunction with reference panel mark-ups


Mortar shallow


Pattern not aligned


Pointing inconsistent


Pointing inconsistent


Assembly Hall low level reference panel- reviewed following modifications


Omit contrasting pointing


As left hand side


Pointing to be more precise where contrasting


Omit additional red brick between motifs


Contrasting pointing to be clearly distinguished


DPC to be cut in Classroom brick (sample shown)