2nd floor classroom blockwork gable underway
Assembly main roof bauder membrane underway
Gap between rooflight and access hatch
Overview of main roof assembly hall
detail of upstand
membrane scuffed- to be addressed
bauder membrane to assembly rooflight upstands
roof membrane underway
Wind posts ground floor classroom block- clerestory openings to follow
Classroom block 2fl corridor in blockwork
double gable elements progressing to classrooms 2fl classroom block
shuttering to underside chimney- to be rectified as not continuous phenyl board
Remedial works to 1fl slab- classroom block
Otway gable end- brickwork details
Otway gables meeting- detail underway- awaiting flashing
Otway gables meeting- detail underway- awaiting fascia/ final brick
Otway ring beam preparation underway high level 1fl perimeter
Cut-out for Otway rooflights