100618 Site Visit


2nd floor classroom blockwork gable underway


Assembly main roof bauder membrane underway


Gap between rooflight and access hatch


Overview of main roof assembly hall


detail of upstand


membrane scuffed- to be addressed


bauder membrane to assembly rooflight upstands


roof membrane underway


Wind posts ground floor classroom block- clerestory openings to follow


Classroom block 2fl corridor in blockwork


double gable elements progressing to classrooms 2fl classroom block


shuttering to underside chimney- to be rectified as not continuous phenyl board


Remedial works to 1fl slab- classroom block


Otway gable end- brickwork details


Otway gables meeting- detail underway- awaiting flashing


Otway gables meeting- detail underway- awaiting fascia/ final brick


Otway ring beam preparation underway high level 1fl perimeter


Cut-out for Otway rooflights