Thursday, 23 December 2010
101223 Site Visit
Assembly Hall- plinth scaffold partially struck
Ditto
Hall from ingrave Road
Windows installed w/ glass- GFL Classroom Block
Ditto
Adjacent Queens- shallow window reveals
Fixing detail CL.EW.00.14- head detail to be discussed- lintel higher internally than external
CL link GFL
Thrislington Sentry panels on site
Window to Praes
Insulation required to brickwork 2FL GL D/1
Acoustic seal to head of block to be completed to 1FL toilets- ceilings already installed
CL.01.25- containment interface with edge bead
CL.EW.02.23 head/ ringbeam to be recast
Assembly plenum now constructed behind bleacher seating
Assembly linings
Minor water damage GL 14 GFL- to be replaced once gutters completed
Assembly linings- structure for hanging acoustic reflector
OT windows GFL- OT.ED.00.04- CVA to confirm scope for refurb
Deputy Head 1 Office
Otway step GL H 1FL- 1 No. course brickwork may need to be reduced- CVA to advise
Chimney- slurry applied/ scaffold removed- Otway 1FL
Otway 1FL ceiling
CVA to confirm whether timber can be removed
Timber structure painting underway. CVA to advise on maintaining void over stair GL G-H
Friday, 17 December 2010
101216 Site Visit
Ceiling light fitting- mock up- 300mm recess to Otway required for fitting
GL Q- clearance required for timber panels/ access for rodding- CVA/ MFLLP to advise
Gas enclosure installed
Stress UK repair completed to 1FL arch Otway
Internal shot of classroom chimney
GFL windows on site awaiting installation
Movement joint to capping- HCL to confirm lapping of DPC where loose capping
Otway gulley detail to Otway gable end
Flashing work requires attention to tidy up- roof to Otway House
Ridge tile fixings/ trim to be tidied up
Scaffold removed to reveal structure + void, Otway House
Ditto
Draught seals installed to windows
Additional rot/ repairs required to windows- HCL to schedule those areas over/ above schedule refurb
Cill colour- CVA to forward
DGT profiles being fitted to classroom rooflights
Classroom block- windows fitted GFL- link sealed
Assembly plantroom- scaffold struck. Grille/ ducts to be adjusted- see SVR
2fl corridor- M&E 1st fix underway
Otway render hacked off and removed where live
Link 1fl- blockwork underway
GFL link- screed completed- movement joints required to Otway/ Classroom
Monday, 13 December 2010
101210 Site Visit
Linings to assembly hall complete- minor water ingress GL N
Assembly stair lining/ cross section to be issued- CVA
Lambs replacement arch underway Otway house
Movement joint required to screed- Classroom link/ Otway threshold GFL
GL E/6 brick plinth to be cut back for curtain walling
First delivery of Secco Windows on site
Ditto
Deeper 'z' section required for fixing of acoustic panel
CVA to forward interface details for Stair 2 balustrade
Movement joint needed between link and classroom block to screed 1FL
Fireproofing underway to CL plantroom 2FL- requires intumescent sealant
Drain in progress 2 FL plantroom
Air tightness detail to be reviewed to corridor 2FL classroom- CVA to update/ clarify
Interfaces/ gaps to be highlighted- 2FL classroom- Classroom 16
Water tank deck/ guarding installed 2FL classroom
Silicon seal to cill to be removed/ redone- Sealant as RAL 7022
DGT flashing profiles now on site for CL rooflights