Ceiling light fitting- mock up- 300mm recess to Otway required for fitting


GL Q- clearance required for timber panels/ access for rodding- CVA/ MFLLP to advise


Gas enclosure installed


Stress UK repair completed to 1FL arch Otway


Internal shot of classroom chimney


GFL windows on site awaiting installation


Movement joint to capping- HCL to confirm lapping of DPC where loose capping


Otway gulley detail to Otway gable end


Flashing work requires attention to tidy up- roof to Otway House


Ridge tile fixings/ trim to be tidied up


Scaffold removed to reveal structure + void, Otway House


Ditto


Draught seals installed to windows


Additional rot/ repairs required to windows- HCL to schedule those areas over/ above schedule refurb


Cill colour- CVA to forward


DGT profiles being fitted to classroom rooflights


Classroom block- windows fitted GFL- link sealed


Assembly plantroom- scaffold struck. Grille/ ducts to be adjusted- see SVR


2fl corridor- M&E 1st fix underway


Otway render hacked off and removed where live


Link 1fl- blockwork underway


GFL link- screed completed- movement joints required to Otway/ Classroom