Ceiling light fitting- mock up- 300mm recess to Otway required for fitting
GL Q- clearance required for timber panels/ access for rodding- CVA/ MFLLP to advise
Gas enclosure installed
Stress UK repair completed to 1FL arch Otway
Internal shot of classroom chimney
GFL windows on site awaiting installation
Movement joint to capping- HCL to confirm lapping of DPC where loose capping
Otway gulley detail to Otway gable end
Flashing work requires attention to tidy up- roof to Otway House
Ridge tile fixings/ trim to be tidied up
Scaffold removed to reveal structure + void, Otway House
Ditto
Draught seals installed to windows
Additional rot/ repairs required to windows- HCL to schedule those areas over/ above schedule refurb
Cill colour- CVA to forward
DGT profiles being fitted to classroom rooflights
Classroom block- windows fitted GFL- link sealed
Assembly plantroom- scaffold struck. Grille/ ducts to be adjusted- see SVR
2fl corridor- M&E 1st fix underway
Otway render hacked off and removed where live
Link 1fl- blockwork underway
GFL link- screed completed- movement joints required to Otway/ Classroom