Monday, 13 December 2010

101210 Site Visit


Linings to assembly hall complete- minor water ingress GL N


Assembly stair lining/ cross section to be issued- CVA


Lambs replacement arch underway Otway house


Movement joint required to screed- Classroom link/ Otway threshold GFL


GL E/6 brick plinth to be cut back for curtain walling


First delivery of Secco Windows on site


Ditto


Deeper 'z' section required for fixing of acoustic panel


CVA to forward interface details for Stair 2 balustrade


Movement joint needed between link and classroom block to screed 1FL


Fireproofing underway to CL plantroom 2FL- requires intumescent sealant


Drain in progress 2 FL plantroom


Air tightness detail to be reviewed to corridor 2FL classroom- CVA to update/ clarify


Interfaces/ gaps to be highlighted- 2FL classroom- Classroom 16


Water tank deck/ guarding installed 2FL classroom


Silicon seal to cill to be removed/ redone- Sealant as RAL 7022


DGT flashing profiles now on site for CL rooflights