Friday, 26 November 2010

101125 Site Visit


Assembly Fireborn blue capping installed to plinth -special corner


ditto


Classroom lift installation underway


Internal brick exposed- but not ibstock- HCL to advise- not as CVA detail


Recessed now skimmed- awaiting wall lights


Light greypointing mortar currently being used to repoint (dabbed in centre) differ from Otway conservation officer approved mortar sample 6:1:1- HCL to advise


2nd floor plant trough underway- CL


Assembly gables in brick nearing completion


CL stairwell rooflight- main stair


CVA to instruct dryline fillet- to be coordinated with 2fl joinery- HCL to advise HTP- to form part of CVA comments on joinery


Containment to class stairs to be shallower bend to allow fixing of acoustic panels to u/side of stair


CVA to forward detail for lining to rooflight/ wall junction


Internal chimney underway classroom 11


trapezoid rooflight installed classroom 11


block awaiting acoustic seal- classroom block 1fl


patterned chimney complete classroom 8


Block/ prop detail to be resolved- GL C/7


TEK vents 1fl- awaiting cills- promised Mon 22 Nov


CVA to check detail of support with HRW


Brickwork badly stained, cill mods required, ringbeam mods required GL 4


GL 4 overview.


Setting out of brick gable geometry GL D to be clarified with HCL


Otway loft linings nearing completion


Otway stair lighting underway


Otway elec containment GFL underway- CVA to check levels/ items against drawings


Roof scape overview


DGT gutter to be modified to corner


DGT flashing closer piece installed


Awaiting adjusted gothic arch bricks from Lambs to be redelivered


Grille/ ducts behind hit and miss brickwork GFL plantroom- deviation from CVA/ MFLLP intent/ comments- HCL to advise


Ditto


Fireline underway to AS plantroom


Plastering underway to AS lobby GFL


Assembly Hall linings to main hall- corner fillets complete


Assembly gables nearing completion