High level brickwork at Assembly Hall approach completion with first gables being finished.

Lintol to first floor link between Otway and Assembly to be installed.

High level ceiling lining to Otway existing structure in first floor lobby. Suspended ceiling to be added.

Hutton to ensure that refurbished existing plaster to be brought back to provide a good key for new plaster.

Final lining to high level Otway ceiling being installed to ensure clean junctions around roof form.

High level exposed roof structure with lining to roof. Area above stair insulated without plasterboard given suspended ceiling below.

Hutton to finish plasterboard lining above PFC with neat beading detail.

Skimming to refurbished ground floor soffit in Otway largely complete. Suspended acoustic ceiling to follow.

Services through main Otway riser to first floor.

Existing cornice timber supports in Otway to be stripped out and plaster made good.

Pipework installed prior to completion of plasterboard. If bulkhead cannot be made to perform in an acceptable acoustic/fire performance, Hutton must propose remedial solution.

Two options for additional new bricks to Otway to match existing. Brick on top agreed to be the best match.

Route of rainwater downpipe in link at the external wall of Otway to be resolved.

Work to restore triple arch in Otway with new Lambs bricks underway.

Completed Assembly Hall gable.

Site dimension confirming capping size is correct. Internal lining to parapet to be resolved.


Internal lining to Assembly Hall underway.

Screed to ancilliary spaces of Assembly along Ingrave Road poured to 50mm below FFL. Additional screed or unobat system required to achieve FFL.

Junction of Mezzanine at External wall of Assembly. Issue of structural design to be resolved.

Hutton to issue Taylor Engineering proposal for supporting internal wall linings.

Support to Assembly mezzanine around RWP needs to be resolved

Plastering to Classrooms ongoing

Acoustic and thermal linings to Classroom chimneys and also structural straps underway.

Rainwater outlets to Classroom, internally routed from gutter largely complete.

Rooflights installed from within 2F classroom.

Hip of roof discussed on site with view to omit ventilated tiles.

Damage to roofing panels, roofer to advise on edge of tiling over gutter.

rooflights installed, fixed to timber bolted down to steelwork below. lead flashing below, awaiting aluminium soaker/upstands to complete flashing.

Row of rooflights installed along Classroom roof, once tiling is on these will be flush with the roof finish.

Area of roof valley where it is proposed to move SVPs.

View of patterned Assembly brick from Ingrave Road.