Status of brickwork to Assembly Hall. Hutton confirm that setting out issues have been addressed. |
Plastering underway on Classroom ground floor |
Condensation to omnia noted on Ground floor classroom ceilings |
Water ingress from above onto newly plastered classroom (ground floor) |
Vertical cladding and cavity wall work to link not yet underway. |
Issue with pipework in front of clerestory |
Run off from roof works along Ingrave road elevation of Classroom Block. Hutton have been advised and will clean. |
Triple arch brickwork has arrived on site ready for installation. |
Fireline to Otway Ground floor ceiling: CVA to confirm if skimming is required above suspended ceiling. |
Otway ceiling linings under way, additional layer of plasterboard required. Insulated lining around rooflights will need to be cut back to achieve splayed reveals with final layer of plasterboard. |
Otway roofing complete, awaiting rainwater goods. |
Vale Interiors have raised a question about the method of hanging the lowered ceiling off the raked structure, particularly the fixing to the primary steel. |
Hutton to ask how internal wall lining & build-up above long opening to Assembly is supported. |
Hutton to ask how floor joists of plenum are picked up at Assembly external wall |