Friday, 15 October 2010
101014 Site Visit
Otway timber paint sample- for client review
Rooflights installed high level- actuator/ cheek detail to be revised- CVA
Additional minor brickwork repairs to be clarified- previously obscured by Scaffold
Chimney in progress
DGT gulley- remedial works required to parapet and interface with gutter GL D
Classroom valley- DGT Kingspan panels installed to lift overrun
Kerb detail
kerb detail completed- sealant detail to be reviewed- CVA/ HCL
Damage to eaves panels- crown/ overlap poorly fitted- HCL to advise
Holes to panel- HCL to advise of remedial work
ditto
Gutter GL4
Gutter GL 4/D
Containment GL 2/3 to top floor classroom- CVA to instruct surface mounted where clashing with upstand- additional joinery plinth to be added below dado- CVA to instruct
Link deck installed
Edge beads added and bonding coat commenced- Praepostors
Insulation to be fitted between ringbeam and roof panel to maintain cavity
Assembly gable brickwork progressing
Ditto
Classroom acoustic vents carcassing/ cills installed GFL
Screed laid to perimeter storage Assembly hall
Conflict to clerestory 1FL classroom block
review chasing of 1 No. light to Stair 1, 1-2FL
Interactive whiteboard spec. updated to pictured model with ancillary speakers and amp...
.... from previous model- CVA to review impact of changes proposed to build/ coordination
secondary grid installation underway
Internal metsec installation underway- note recesses formed for acoustic panels
Ditto