Friday, 15 October 2010

101014 Site Visit


Otway timber paint sample- for client review


Rooflights installed high level- actuator/ cheek detail to be revised- CVA


Additional minor brickwork repairs to be clarified- previously obscured by Scaffold


Chimney in progress


DGT gulley- remedial works required to parapet and interface with gutter GL D



Classroom valley- DGT Kingspan panels installed to lift overrun


Kerb detail


kerb detail completed- sealant detail to be reviewed- CVA/ HCL


Damage to eaves panels- crown/ overlap poorly fitted- HCL to advise


Holes to panel- HCL to advise of remedial work


ditto


Gutter GL4


Gutter GL 4/D


Containment GL 2/3 to top floor classroom- CVA to instruct surface mounted where clashing with upstand- additional joinery plinth to be added below dado- CVA to instruct


Link deck installed


Edge beads added and bonding coat commenced- Praepostors


Insulation to be fitted between ringbeam and roof panel to maintain cavity


Assembly gable brickwork progressing


Ditto


Classroom acoustic vents carcassing/ cills installed GFL


Screed laid to perimeter storage Assembly hall


Conflict to clerestory 1FL classroom block


review chasing of 1 No. light to Stair 1, 1-2FL


Interactive whiteboard spec. updated to pictured model with ancillary speakers and amp...


.... from previous model- CVA to review impact of changes proposed to build/ coordination


secondary grid installation underway


Internal metsec installation underway- note recesses formed for acoustic panels


Ditto