Friday, 8 October 2010

101007 Site Visit


Steel installed Otway GL I


Chimney brickwork paused- awaiting installation of roof panels


Gutter awaiting overflow- HCL to advise regarding rigid insulation between parapet and gutter


Kingspan KTS 1000 panels installed GL 9


Assembly hall plinth overview


Chimney/ ringbeam cutting underway


DGT gutter GL 1- aluminium leg to gutter too high in relation to parapet- HCL to advise


Gutter GL 1


HRW to review lintel calcs- minor crack to mortar GL C brickwork 1FL


Thermal bridge- chimney base cast incorrectly- details revised accordingly to eliminate


Roofscape overview from Assembly- Otway valley rooflights now fitted


Ball guards now installed Assembly Hall


South Elev brickwork assembly- GL Q


GL Q/ 16 high level parapet relief work


GL 14 brickwork now underway


Assembly hall ceiling installed inc. drop rods- + mist coat


Classroom 11 awaiting internal chimney/ roof panels


Classroom link- floor deck installed


ditto


View of Assembly Hall from Praes