Friday, 8 October 2010
101007 Site Visit
Steel installed Otway GL I
Chimney brickwork paused- awaiting installation of roof panels
Gutter awaiting overflow- HCL to advise regarding rigid insulation between parapet and gutter
Kingspan KTS 1000 panels installed GL 9
Assembly hall plinth overview
Chimney/ ringbeam cutting underway
DGT gutter GL 1- aluminium leg to gutter too high in relation to parapet- HCL to advise
Gutter GL 1
HRW to review lintel calcs- minor crack to mortar GL C brickwork 1FL
Thermal bridge- chimney base cast incorrectly- details revised accordingly to eliminate
Roofscape overview from Assembly- Otway valley rooflights now fitted
Ball guards now installed Assembly Hall
South Elev brickwork assembly- GL Q
GL Q/ 16 high level parapet relief work
GL 14 brickwork now underway
Assembly hall ceiling installed inc. drop rods- + mist coat
Classroom 11 awaiting internal chimney/ roof panels
Classroom link- floor deck installed
ditto
View of Assembly Hall from Praes