Friday, 1 October 2010
100930 Site Visit
Lime mortar pointing sample
Valley rooflights installed in Otway
Roof steel interface query- HCL- assembly/ Otway high level link steel
Lightning protection strike pad/ new slates
Dry-fix ridge requires trimming/ mortar fill to allow fitting of perimeter gutters
Ditto
1st fix electrical to 1st floor Otway
Steel installation adjacent link underway- Otway
Tile finishes still remain unprotected Otway Ground Floor
As a result tile finishes are now damaged and will require repair
Mech 1st fix Otway in progress- routes revised
Assembly toilets- Door openings/ linings to be amended
Ceiling high level installed
DGT remedial works unacceptable- DGT/ HCL to advise regarding warranty/ completion
Rooflights high level assembly installed
Ditto
Lintels GL 18 Assembly installed but discrepancy between installations- HCL to advise regarding finer details of installation of brick slips/ packing/ propping method etc.
Blockwork to be completed GL Q/ 20
GL Q/14 relief corner completed
HCL to confirm acceptable clearance 28mm tophat section will fit.
HCL to confirm spec. of change in blockwork spec.
Chimney brickwork progressing GL 1/ C
Angle protrusion/ support to facing brickwork GL 1/B-C
Firestopping required above door linings- classroom block
Marking out of recessed lighting to stairwells- classroom block
TSI revised detail to link junction
Neoprene spacers now installed to chimney facework ties
brickwork parapet level GL C classroom- damaged by scaffold
Valley gutter installed
DGT detail amended without approval to now include quilt insulation- CVA to investigate/ advise
Gutters to perimeter GL A now fitted