Otway arch- still awaiting final Lambs drawings- no progress
Mortar pointing samples- on inconsistent/ stock bricks- additional samples to be carried out
lead/ gable detail underway Otway
Arch OT.01.15 still unpropped following damage
New slates underway
Valley detail underway
Insect mesh detail
First fix, secondary floor joists 1st floor Otway
First fix/ penetrations High level ground floor Otway
Different block specification- not Plasmor- HCL to confirm
GL A/7 reveal detail to be updated due to TEK cill detail/ movement joint
Ditto CL.EW.02.04
Ditto CL.EW.02.07
Raked cut to GL 4 high level
Link steelwork
Valley gutter installation underway classroom block
Remedial works to ties now undertaken
TEK to clarify strategy for Attenuated vent installation procedure
High level obstruction to attenuated vents 2nd floor- HCL to clarify fixing to underside of ringbeam
rods to be trimmed to allow acceptable tolerance for TEK vent
Openings for chimneys required high level ground floor GL B and C/ 1
CVA to confirm brick slips to concrete chimney base face
CVA to forward canopy detail, HRW to update structural connection
Chimney tie remedials underway
Ditto
Engineering brick penetrations- HCL to confirm possible remedial works to amend with FOSROC
Issue with high level steelwork to assembly mezzanine/ build up/ Vales works
Assembly hall ceiling 1st layer under installation
Classroom/ Otway overview
Assembly hall 1st floor lintels on site- HCL to forward brick slip details/ specs for comment
DGT expanding foam detail to valleys
Brick reveals underway GL 18 Assembly
GDT profile to be added to all locations where remedial works are underway
BJR to corners, GL Q/18
'V' detail GL Q/16 underway
High level corner nearing completion GL Q/14