Friday, 24 September 2010

100923 Site Visit


Otway arch- still awaiting final Lambs drawings- no progress


Mortar pointing samples- on inconsistent/ stock bricks- additional samples to be carried out


lead/ gable detail underway Otway


Arch OT.01.15 still unpropped following damage


New slates underway


Valley detail underway


Insect mesh detail


First fix, secondary floor joists 1st floor Otway


First fix/ penetrations High level ground floor Otway


Different block specification- not Plasmor- HCL to confirm


GL A/7 reveal detail to be updated due to TEK cill detail/ movement joint


Ditto CL.EW.02.04


Ditto CL.EW.02.07


Raked cut to GL 4 high level


Link steelwork


Valley gutter installation underway classroom block


Remedial works to ties now undertaken


TEK to clarify strategy for Attenuated vent installation procedure


High level obstruction to attenuated vents 2nd floor- HCL to clarify fixing to underside of ringbeam


rods to be trimmed to allow acceptable tolerance for TEK vent


Openings for chimneys required high level ground floor GL B and C/ 1


CVA to confirm brick slips to concrete chimney base face


CVA to forward canopy detail, HRW to update structural connection


Chimney tie remedials underway


Ditto


Engineering brick penetrations- HCL to confirm possible remedial works to amend with FOSROC


Issue with high level steelwork to assembly mezzanine/ build up/ Vales works


Assembly hall ceiling 1st layer under installation


Classroom/ Otway overview


Assembly hall 1st floor lintels on site- HCL to forward brick slip details/ specs for comment


DGT expanding foam detail to valleys


Brick reveals underway GL 18 Assembly


GDT profile to be added to all locations where remedial works are underway


BJR to corners, GL Q/18


'V' detail GL Q/16 underway


High level corner nearing completion GL Q/14