Friday, 17 September 2010
100916 Site Visit
Overview from Ingrave Road
Classroom block gable brickwork underway to courtyard
Fixings for secondary grid- assembly hall
Area for remaining bricks lift to assembly- to commence shortly
DGT profiles adjacent gutters to be fitted- assembly roof
GL Q/14- bricks marked up to corner for amendments following previous comments
GL 18 brick reveals assembly hall
Corner underway GL Q/18
Latchway system installed to Bauder roof assembly hall
Assembly rooflights awaiting installation- main roof
Rooflight detail (to be rotated 180ยบ before installation)
Otway gable end (new facing brick) revealed
Arch repairs first floor Otway revealed
Lead detail against rebuilt chimney Otway
Valleys introduced Otway
Arch repair imminent- condition worsened
Bed joint reinforcement installed gable end classroom- courtyard
Block to be cut GL K/20
Protection to door linings classroom block
Link steel installed
High level raked steel angle trim
Possible service clash 1st floor classroom- CVA to advise regarding clerestory set out
Joinery schedule to be updated re: clerestory lights
TEK vent/ reveal
Concrete upstand detail- acoustic panel/ interface/ bead detail to be reviewed
Concrete remedials underway to chimney base classroom
Assembly overview- plinth
timber structure for rooflights underway
Pattern brick to chimneys internally- classroom block
DGT gutter installation underway- classroom block
Ties- cracking to ringbeam GL C
TSI remedials to trapezoid rooflight area
further tolerance req'd to top steel- HCL to fwd fixing detail option for HRW review
ditto
Floor joists first floor Otway
Link steelwork classroom/ Otway
Stanchion/ recess infill- CVA to confirm detail re: LAC support
Gutter for classroom on site
tolerance for linings to be reviewed
Link steel connection
Main chimney brickwork/ ringbeam interface
Chimney brickwork- movement joint
Link overview
Repair to corner underway- Queens