Ceiling installation underway to hall


Fixings to noggins- to be addressed by Vales


Joist hangers loose- to be addressed


ditto


DGT remedial work underway to Assembly roof


Fixing of secondary grid questioned- type/ method/ loading tbc by Vales


Assembly ceiling setting out may be too low- in relation to gable linings. HUT to advise


Principles of windpost setting out confirmed on site- HRW to confirm in writing


ditto


Chimney base still to be resolved by AJC/ HUT prior to internal brickwork


Screed to be adjusted to assembly plant threshold


pitting to Omnia- highlighted by mist coat- CVA to advise


Mech/ elec services within bulkhead area of classroom


Door linings classroom block


ditto


Trapezoid rooflight opening- classroom


Large chimney steelwork erected- CL.RL.03.05 snagging block wall- CVA to advise


Chimney steelwork


concrete spalling- HRW to advise


Ringbeam and steelwork now in place


Otway nib GL H/12- penetration required for radiator


Greater protection for retained floor finishes required- ACTION HUT


builderswork to be relocated- penetration under pier at present- GL H/12


Otway Velux rooflights on site