Friday, 3 September 2010
100902 Site Visit
Ceiling installation underway to hall
Fixings to noggins- to be addressed by Vales
Joist hangers loose- to be addressed
ditto
DGT remedial work underway to Assembly roof
Fixing of secondary grid questioned- type/ method/ loading tbc by Vales
Assembly ceiling setting out may be too low- in relation to gable linings. HUT to advise
Principles of windpost setting out confirmed on site- HRW to confirm in writing
ditto
Chimney base still to be resolved by AJC/ HUT prior to internal brickwork
Screed to be adjusted to assembly plant threshold
pitting to Omnia- highlighted by mist coat- CVA to advise
Mech/ elec services within bulkhead area of classroom
Door linings classroom block
ditto
Trapezoid rooflight opening- classroom
Large chimney steelwork erected- CL.RL.03.05 snagging block wall- CVA to advise
Chimney steelwork
concrete spalling- HRW to advise
Ringbeam and steelwork now in place
Otway nib GL H/12- penetration required for radiator
Greater protection for retained floor finishes required- ACTION HUT
builderswork to be relocated- penetration under pier at present- GL H/12
Otway Velux rooflights on site