101118 Site Visit
Assembly Hall GL 18 brickwork- gables now complete- awaiting Fireborn capping
Ditto
Decorative brickwork infill panel GL D/3 nears completion
1fl TEK vents delivered/ installation underway
TEK sill incorrect angle- TEK addressing and re-manufacturing/ fitting
Ditto
Containment/ fixing of cable tbc with MFLLP
Reveals to rooflights- Otway loft internal
Recessed lights to stairwell- Otway
beading details to Otway loft- awaiting plaster skim
Assembly lining underway- corner fillets to be completed. Vales/ Taylor engineering to confirm details for hanging fixings to raked internal lining GL P-Q
Hairline crack to brick horizontally over Ancon brickwork support GL 14- HRW to advise
Special bricks glued to lintol GL 18. HCL to forward tech specs/ method- still outstanding
Corner/ parapet GL Q/18. Timber/ insulation installation underway. DGT gutter to be cute down. Parapet awaiting Capping.
Ibstock Fireborn cappings now on site.
Gable detail GL 9- clearance acceptable
Inadequate clearance to brick upstand GL 1
Ditto
Gutter lower than outlet position- GL D/4
GL D/1- outlet finishing poor- HCL to advise
Ditto
Ditto
Internal gutter level to be lowered to parapet level- HCL to advise
Ditto
Edge detail poorly cut- HCL to advise
Hip detail refitted but GRP detail still tbc- HCL to advise
Outlet/ falls to valley gutter inadequate- HCL to advise
Detail/ intent not as CVA DWG CL330 PL01 + notes.- HCL to advise