Friday, 19 November 2010

101118 Site Visit


Assembly Hall GL 18 brickwork- gables now complete- awaiting Fireborn capping


Ditto


Decorative brickwork infill panel GL D/3 nears completion


1fl TEK vents delivered/ installation underway


TEK sill incorrect angle- TEK addressing and re-manufacturing/ fitting


Ditto


Containment/ fixing of cable tbc with MFLLP


Reveals to rooflights- Otway loft internal


Recessed lights to stairwell- Otway


beading details to Otway loft- awaiting plaster skim


Assembly lining underway- corner fillets to be completed. Vales/ Taylor engineering to confirm details for hanging fixings to raked internal lining GL P-Q


Hairline crack to brick horizontally over Ancon brickwork support GL 14- HRW to advise





Special bricks glued to lintol GL 18. HCL to forward tech specs/ method- still outstanding


Corner/ parapet GL Q/18. Timber/ insulation installation underway. DGT gutter to be cute down. Parapet awaiting Capping.


Ibstock Fireborn cappings now on site.


Gable detail GL 9- clearance acceptable


Inadequate clearance to brick upstand GL 1


Ditto


Gutter lower than outlet position- GL D/4


GL D/1- outlet finishing poor- HCL to advise


Ditto


Ditto


Internal gutter level to be lowered to parapet level- HCL to advise


Ditto


Edge detail poorly cut- HCL to advise


Hip detail refitted but GRP detail still tbc- HCL to advise


Outlet/ falls to valley gutter inadequate- HCL to advise


Detail/ intent not as CVA DWG CL330 PL01 + notes.- HCL to advise

No comments: