Monday, 15 November 2010
101111 Site Visit
DGT gutter works/ interface require additional work GL D/1
DGT/ HCL to advise over quality of hip formed GL B/1
Ditto
Flashings/ rooflights underway Classroom block GL C
Trapezoid rooflight frame installation underway GL4
Underside of trapezoid rooflight
Otway query- upper sash fixed/ sealed? CVA to confirm
CVA to confirm fire-lining of ceiling/ duct where ceiling not continuous
Gable end arch replacement underway
OT.EW.01.03- arch specified to be reused not retained. HCL to forward quote for replacement asap.
Otway linings near completion to loft
Scaffold to arch- Otway gable end
Classroom roof panels installed
Link roof carpentry complete
Riser 1- CVA to clarify boiler flue penetration
Plantroom classroom block- CVA to clarify fire-stopping/ acoustic seal
Contraction joint to blockwork- plaster detail- classroom block GFL corridor
Site painting- acoustic louvre- TEK completed
Soffit GFL- condensation throughout- CVA to monitor
Special bricks to lintel- assembly hall GL 18
Brickwork to gables complete- GL Q
Brickwork GL Q
Concrete fill to be completed- GL 14
GL L/14 parapet nearing completion
Confirmation required to internal lining support- 1st floor assembly
Linings to assembly hall nearing completion- CVA to confirm low level air-tightness
High level ducts installed
Linings assembly hall
ditto
door linings to assembly lobby
fan coil unit to assembly toilet soffit
Penetrations for light fittings to assembly- HCL to ensure good seal around fittings when installed