Monday, 15 November 2010

101111 Site Visit


DGT gutter works/ interface require additional work GL D/1


DGT/ HCL to advise over quality of hip formed GL B/1


Ditto


Flashings/ rooflights underway Classroom block GL C


Trapezoid rooflight frame installation underway GL4


Underside of trapezoid rooflight


Otway query- upper sash fixed/ sealed? CVA to confirm


CVA to confirm fire-lining of ceiling/ duct where ceiling not continuous


Gable end arch replacement underway


OT.EW.01.03- arch specified to be reused not retained. HCL to forward quote for replacement asap.


Otway linings near completion to loft


Scaffold to arch- Otway gable end


Classroom roof panels installed


Link roof carpentry complete


Riser 1- CVA to clarify boiler flue penetration


Plantroom classroom block- CVA to clarify fire-stopping/ acoustic seal


Contraction joint to blockwork- plaster detail- classroom block GFL corridor


Site painting- acoustic louvre- TEK completed


Soffit GFL- condensation throughout- CVA to monitor


Special bricks to lintel- assembly hall GL 18


Brickwork to gables complete- GL Q


Brickwork GL Q


Concrete fill to be completed- GL 14


GL L/14 parapet nearing completion


Confirmation required to internal lining support- 1st floor assembly


Linings to assembly hall nearing completion- CVA to confirm low level air-tightness


High level ducts installed


Linings assembly hall


ditto


door linings to assembly lobby


fan coil unit to assembly toilet soffit


Penetrations for light fittings to assembly- HCL to ensure good seal around fittings when installed