Thursday, 23 December 2010
101223 Site Visit
Assembly Hall- plinth scaffold partially struck
Ditto
Hall from ingrave Road
Windows installed w/ glass- GFL Classroom Block
Ditto
Adjacent Queens- shallow window reveals
Fixing detail CL.EW.00.14- head detail to be discussed- lintel higher internally than external
CL link GFL
Thrislington Sentry panels on site
Window to Praes
Insulation required to brickwork 2FL GL D/1
Acoustic seal to head of block to be completed to 1FL toilets- ceilings already installed
CL.01.25- containment interface with edge bead
CL.EW.02.23 head/ ringbeam to be recast
Assembly plenum now constructed behind bleacher seating
Assembly linings
Minor water damage GL 14 GFL- to be replaced once gutters completed
Assembly linings- structure for hanging acoustic reflector
OT windows GFL- OT.ED.00.04- CVA to confirm scope for refurb
Deputy Head 1 Office
Otway step GL H 1FL- 1 No. course brickwork may need to be reduced- CVA to advise
Chimney- slurry applied/ scaffold removed- Otway 1FL
Otway 1FL ceiling
CVA to confirm whether timber can be removed
Timber structure painting underway. CVA to advise on maintaining void over stair GL G-H