Friday, 7 January 2011

110106 Site Visit


Tape and jointing proceeding to Assembly Hall- HCL to advise regarding water ingress/ plasterboard damage/ replacement


Otway 1fl high level.


Overview of classroom courtyard. DGT completing roof works


Classroom sentry panel installation underway to WCs GFL


Ditto


Mineral wool to chimney sodden/ damaged. HCL to advise regarding replacement


Chimney brickwork to classroom 1fl nearing completion


GL C/7- HCL to advise regarding completion


Acoustic seal required- Classroom block blockwork


Secco windows- rubber seals too narrow for glass- to be rectified- HCL to advise


Internal head detail/ reveal to be confirmed- discrepancies in levels


Ditto. CVA/ HCL to review current provision for reveal linings/ treatment