Monday, 24 January 2011
110120 Site Visit
Otway Door lining queries- depth agreed- HCL to liaise with Shadbolts to confirm
CVA drawing denotes arch- CVA to confirm treatment to GFL Otway opening
AS green room wall commenced
Secco glazing on site
HTP samples on site-
WISA joinery sample door
Birds mouth detail stair panel option
Shadow gap detail stair panel option
CL roof battens underway
GRP nearing completion to CL roof
Battening to valley- CL block
Roofing detail not as Kingspan recommended- issued as transmittal K444, issued 12 Oct, '10
Battens to roof classroom block
Closer piece to be fitted by DGT
Blockwork to GL 14 underway for Fineline windows
AS Insulation/ flashing to parapet complete
Ply to underside of GL14 opening AS
AS mezzanine framing underway
Mist coat underway AS main hall
Vales mezzanine framing AS 1st floor
Brickwork to AS green room underway
Brick plinth to Ingrave Road- Scaffold struck
Classroom block- timber battening to roof
Teapoint door lining to Otway
Otway high level 1fl
2 coats to timber trusses
Slurry applied to chimney high level 1fl Otway
Ditto
Ditto
CVA confirmed to recess finish of infill boarding 50mm from slurried chimney
Ditto
Mech/ Elec access limited 2fl CL
Ditto- CVA to confirm if bulkhead required for electrical route into plantroom
Electrical 1st fix underway 2fl CL
Plastering 2fl CL
CVA to confirm lining around framing- Classroom 16 2fl
Rooflights Classroom 11
Large chimney- internal finish brickwork nearing completion
Classroom link- block complete
CVA to forward agreed detail for window boards/ linings
Tiling detail to toilets
Chimney internal insulation
Classroom 4 cabling
Otway roof remedials complete- CVA to check on site